Iowa DOT Project Management Peer Exchange

Thumbnail Image
Date
2016-07-01
Authors
Shane, Jennifer
Major Professor
Advisor
Committee Member
Journal Title
Journal ISSN
Volume Title
Publisher
Authors
Person
Shane, Jennifer
Associate Professor
Research Projects
Organizational Units
Organizational Unit
Institute for Transportation
InTrans administers 14 centers and programs, and several other distinct research specialties, and a variety of technology transfer and professional education initiatives. More than 100 Iowa State University faculty and staff work at InTrans, and from 200 to 250 student assistants from several ISU departments conduct research while working closely with university faculty. InTrans began in 1983 as a technical assistance program for Iowa’s rural transportation agencies.
Journal Issue
Is Version Of
Versions
Series
Department
Institute for Transportation
Abstract

This project supported the planning and conduct of a two-day Iowa Department of Transportation–hosted peer exchange for state agencies that have implemented some or all of the suggested strategies outlined in the Second Strategic Highway Research Program–sponsored project R10, Project Management Strategies for Complex Projects.

Presentations were made by participating states, and several opportunities were provided for directed discussion. General themes emerging from the presentations and discussions were identified as follows:

  1. To implement improvements in project management processes, agency leadership needs to decide that a new approach to project management is worth pursuing and then dedicate resources to developing a project management plan.
  2. The change to formalized project management and five-dimensional project management (5DPM) requires a culture shift in agencies from segmented “silo” processes to collaborative, cooperative processes that make communication and collaboration high priorities.
  3. Agencies need trained project managers who are empowered to execute the project management plan, as well as properly trained functional staff.
  4. Project management can be centralized or decentralized with equal effect.
  5. After an agency’s project management plan and structure are developed, software tools and other resources should be implemented to support the plan and structure.
  6. All projects will benefit from enhanced project management, but the project management plan should specify appropriate approaches for several project levels as defined by factors in addition to dollar value.
  7. Project management should be included in an agency’s project development manual.

Comments

For this and other reports, visit the InTrans project page at http://www.intrans.iastate.edu/research/projects/detail/?projectID=-1843802483